Post contract works
Issue date January 2017
Additional works which are requested by the client at a late stage and which could cause the original contract completion date to over run are to be organised as follows:
- Obtain written confirmation of funding for the additional works from the client. Then either:
- Instruct the contractor to carry out the items as post contract works having agreed with him in advance the conditions and cost.
Or - Supply drawings, confirmation of funding and specification where appropriate to the FM single service provider who will arrange for the work to be carried out by the maintenance team/contractor.
- Instruct the contractor to carry out the items as post contract works having agreed with him in advance the conditions and cost.
The above policy is intended to avoid the situation where the works are incorporated in the contract by issuing a variation order with the client's written approval and which then results in the principal contractor applying for an extension of time and claiming overheads and profits accordingly.